Communication Manager Maintenance-Object Repair Procedures
2458 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
2000 ABRT Response to the test was not received within the allowable time period. This
may be due to hyperactivity. Error Type 1538 in the error log indicates
hyperactivity. The hyperactive circuit pack is out of service, and one or more
of the following symptoms may be exhibited.
The UDS1-BD tests (such as Tests #138 and #139) are aborting with
Error Code 2000.
The tests run on the ports of this circuit pack are returning a no-board
result.
A busyout or a release command has no effect on the test results.
A list config shows that the circuit pack and its ports are
properly installed.
When hyperactivity occurs, the circuit pack is isolated from the system, and
all of its trunks are placed into the out-of-service state. The system will try to
restore the circuit pack within 15 minutes. When no faults are detected for
15 minutes, the UDS1 interface circuit pack is restored to normal operation.
Every UDS1 Interface trunk is then returned to the in-service state.
Hyperactivity is often caused by the associated facility. In such a case,
faults (such as slips, misframes, or blue alarms) would be entered in the
error log. In addition, many hardware errors would be logged against the
associated trunk circuits. If the facility is OK and the error occurs again after
15 minutes, replace the circuit pack.
2100 ABRT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals up to 5 times.
2 FAIL The CLJ-LB test failed because it was not set up properly. The UDS1
interface pack could not successfully put the CPE loopback jack into
loop-back mode.
1. Rerun test ds1-loop location
cpe-loopback-jack-test-begin
2. If the test continues to fail, the problem could be with the UDS1-BD
board, the CPE loopback jack equipment, or somewhere between.
Run test ds1-loop location ds1/csu-loopback-tests to
determine whether the loop-back tests that are closer to the UDS1-BD
board are successful. If any of these tests fail, follow the maintenance
strategy that is associated with the failing test.
Table 870: Test #1212 CPE Loop-Back Jack Test (continued)
Error
Code
Test
Result
Description / Recommendation
3 of 4