75
8.9 PLC for general equipment set-up
Set the functions for the PLC for general equipment, and information on the general equipment
connected to the PLC for general equipment monitored by this integrated software TG-2000A.
8.9.1 Setting Procedure and Restrictions
Before setting the PLC for general equipment, check the precautions.
[Procedure]
1) Click the [PLC for general equipment Set-up] button.
From the initial window, click the [PLC for general
equipment Set-up] button in the System Settings group.
2) Click the [OK] button after checking the display
contents.
Check the details displayed in the warning, and then
click the [OK] button.
* When the [Cancel] button is clicked, this setting is terminated to
return to the initial window.
The PLC for general equipment is set in the following
order.
Step 1 Number of PLC unit set-up
Step 2 PLC set-up and initial setting
Step 3 Function setting
Step 4 Advanced setting (air conditioner status monitor setting)
Step 5 Advanced setting (peak cut function setting)
Step 6 General equipment set-up
8.9.2 Number of PLC unit set-up (Step 1)
Set the number of connected PLC units.
[Procedure]
1) Select the number of connected PLC units.
Select the number of connected PLC units by
clicking “
/
” button.
Number of connected units: 1 to 20 units
* This value can be input from the keyboard.
2) Click the [OK] button.
After making the settings, click the [OK] button.
* When the [Cancel] button is clicked, this setting is terminated
to return to the initial window.
Number of unit
set-up buttons
Number of PLC unit set-up screen
Preparation screen