49
Displays the operation contents of the select buttons on each setting screen.
Buttons Operation contents
[OK]
Validates the contents set on this display screen to advance to the next setting screen.
(Advances to the next setting screen if it is the preparation screen.)
[Next] Advances to the next setting screen.
[Back]
Invalidates the contents set on this display screen to return to the last screen.
[Cancel] Invalidates the contents set on this display screen to shift to the initial screen.
8.2 System Setting Procedure
The following is an explanation of the System Settings performed at the Initial window.
When no System Settings exist
User setting group
Step 1: "User set-up"
Step 2: "Site name set-up"
Step 3: "Password set-up"
System setting group
Step 4: "AG-150A/G-50A connection set-up"
Step 5: " DIDO, AI and PI controller set-up" *5
Step 6: "System configuration set-up"
Step 7: "PLC for General Equipment set-up"
*1, *2, *4
Step 8: "Monitoring screen set-up"
Step 9: "
Measurement meter set-up" *3
Step 10: "
Energy monitoring set-up" *3
Step 11: "Charge set-up" *3
Step 12: "Energy-saving set-up" *4
Step 13: "Night mode set-up"
Step 14: "System-changeover set-up"
Step 15: "IC I/O signal set-up" *2
Step 16: "Time set-up"
*1: This must be set when using the general equipment.
*2: These items must be set when using the general equipment (IC I/O signal).
*3: These items must be set when using the power apportionment billing function. The " Measurement
meter set-up" step is not required when using only the power apportionment billing (manual electric
amount input) function.
*4: This item must be set when using the energy saving or peak cut functions.
*5: This item must be set when using the DIDO, AI and PI controller.
* Even if the AG-150A/G-50A is not actually connected, it is possible to set it in advance as long
as information such as system configuration, etc. is available.
When System Settings exist
Make any changes to the settings.
Caution:
• If the settings are done out of order, some items will not be available and others will have to
be set again.
• Time set-up and Site name set-up are only performed when necessary. Check the time fo
r
each AG-150A/G-50A with “Time set-up”, and set the time when necessary. For "Time
set-up" check the time of each AG-150A/G-50A and PLC, and set the time if necessary.
If the time is set incorrectly, the function does not work properly.
• Even if the operation settings are unclear, set all of the system setting items that appear.
Note:
• Changing certain settings affects the status of other settings.
• User set-up in particular affect other settings and functions.
• Changing the settings on the left affects the settings on the right.
Change and setting items Items that must be confirmed (affected items)
1 "System configuration set-up"
"Monitoring screen set-up", "Energy monitoring set-up"
“Night mode set-up”,”System-changeover set-up”
2 "PLC for General Equipment set-up" "Monitoring screen set-up"
3 "Monitoring screen set-up" "Energy monitoring set-up"
4
" Measurement meter set-up "
(“Watt hour meter set-up”)
"Energy monitoring set-up", "Energy saving set-up"