15
4.6 Step 4: Test operation from integrated centralized control software TG-2000A
Perform the test operation from the integrated centralized control software TG-2000A to check the
operation state and monitor display of the air conditioner.
For the operation procedure, refer to the Instruction Manual (Management).
Note:
• For confirmation in the test operation, use the checklist shown in Chapter 11.
• Perform the normal operation from the integrated centralized control software TG-2000A to
execute the test operation/confirmation. (The test operation function is not included in the
start/stop function.)
Maintenance Tip
• When carrying out test run with the general equipment, so not start and stop the site devices
without approval from the device's controller or work supervisor. Ask that person to witness
the test run.