14
(2) Installing the electric amount count software or PLC for general equipment software or PLC for
demand input
Format the PLC memory, and install the electric amount count software or PLC for general
equipment software or PLC for demand input software to count the power rate pulses with the PLC
or to use the general control or peak cut functions.
4.5 Step 3: Initial setting of integrated centralized control software TG-2000A
(1) Set-up of integrated centralized control software TG-2000A
Make preparations to allow the computer to be operative in order to install the integrated centralized
control software TG-2000A. After performing the set-up preparations, set up the integrated
centralized control software TG-2000A.
(2) Check the AG-150A/G-50A IP address and computer (which uses the integrated centralized control
software)
Check the AG-150A/G-50A IP address. Check the IP address used for the integrated centralized
control software at the same time. Normally, set the sub-net to "255.255.255.0".
Set the integrated centralized control software's IP address, etc., using the Windows(OS)
network setting function.
For a LAN dedicated to the AG-150A/G-50A system, it is recommended to set the IP address
within the following range.
Models IP address range
AG-150A/G-50A main unit [192.168.1.1] to [192.168.1.40]
Computer for browser [192.168.1.101] to [192.168.1.149]
Computer for integrated centralized control software [192.168.1.150]
PLC [192.168.1.151] to [192.168.1.200]
PLC for electric amount count software [192.168.1.151] to [192.168.1.155]
PLC for general equipment PLC software [192.168.1.171] to [192.168.1.190]
PLC for demand input PLC software [192.168.1.191] to [192.168.1.194]
Computer of initial setting tool [192.168.1.201]
* To connect to the existing LAN, set the IP address and sub-net mask set by the LAN manager.
(3) LAN connection confirmation
Check that the LAN cable is connected to the AG-150A/G-50A, computer (using integrated
software), and hub, and that power is supplied to the hub.
(4) Initial setting of integrated centralized control software
Start the integrated centralized control software TG-2000A to execute the initial setting.
Note:
• For the set-up procedure, refer to Chapter 5.
• For safety, check the installation state/connection before turning the power ON.
Note:
• For the initial setting method of the integrated centralized control software TG-2000A, refer to
Chapters 6 to 8.
• In a system using a PLC, initialize the PLC with the integrated centralized control software
TG-2000A so that the PLC can be used.
Note:
• Refer to the installation manuals enclosed with the electric amount count software or PLC fo
r
general equipment software or PLC for demand input software.