10.2.3 COMMISSIONING CHECKLIST
The following checklist should have been completed and supplied by the manufacturer. It
should be placed with other System Configuration Information. Commissioning staff should
check the installed FIP against it. (Note that all pcbs are electronically tested and adjusted
before being fitted to the FIP).
1. CABINET & GENERAL
A) Cabinet colour - Standard Cream Wrinkle (BFF 998 CW)
- Other: ____________________________________
B) Cabinet undamaged (Paint OK)
C) Door aligned correctly
D) Window undamaged and fitted correctly
E) MCP fitted and undamaged
F) Cabinet Door locks firmly, operates microswitch
G) Lock - 003 Type & two keys supplied
H) Door seals fitted to top and sides
I) Display Keypad and 4U door fitted & aligned correctly
J) Cardframe fitted, card fits frame correctly ..(FP0551 only)
K) Standoffs fitted to cabinet rear (none missing)
L) Operator Manual and battery leads included
M) VIGILANT label completed, fitted
2. PCBS & WIRING
A) MAF/PSU Fitted securely on standoffs
B) Controller/Display fitted securely
C) 8ZM fitted securely, earth screw fitted
D) FRC Looms fitted correctly
E) MCP & door switch wires fitted to J6 of MAF/PSU, secured
F) Earth wire fitted to display door