Document No: LT0122 F3200 Installation & Programming Manual
Alignment, Adjustment & Placing into Operation
Issue 2.7 5 July 2001 Page 10-3
10.2 PLACING INTO OPERATION
10.2.1 GENERAL
This chapter describes the procedure to place an F3200 FIP into operation. It assumes that
the mains and other field wiring has been connected, but that the battery has not. Note that
all electronic modules were tested and adjusted in the factory and should need no further
adjustment.
Before switching on power, inspect the cabinet and internals. Check as follows:
1. Check that all equipment is securely mounted, and that all cables are connected at
the appropriate points. The factory checklist is included.
2. Check that the 8 way modules and (if required) the 16 Zone LED Displays are fitted
and connected correctly. (See Sections 2.3.2, 5.2 and 8.1).
3. Check that (if required) the additional battery test resistors, 6A power supply and
overcurrent protection device are fitted as per Chapter 5 (with PTCs shorted). Note
that batteries are not yet connected.
4. Check that links Lk2-4 on the MAF are fitted (unless Anc3, clean contacts is being
used), and module relay supervision links are fitted in the S position for relays which
require supervision.
5. Check that the field wiring of AZC and relays is as per the "As Built" wiring diagrams
and corresponds to the configuration of modules and links.
The "MAINS ISOLATE SWITCH" is located at the top right hand side of the cabinet rear, to
the left of the mains transformer, behind the inner display door. This controls the mains
power to the FIP, charger and power supply, and should be left on once the FIP is
operational.
NOTE: The Battery is not disconnected by the "MAINS ISOLATE SWITCH".