10.2.2 POWER UP
To place the F3200 FIP into operation, perform the following steps:
STEP 1 Ensure that the Mains Isolate Switch is OFF.
STEP 2 Ensure that 240 VAC is connected to the panel from the mains distribution
switchboard.
STEP 3 Ensure that Lk7 on the controller is set to the DATABASE WRITE PROTECT
position before powering on the panel. If an E2INIT is required before
programming, fit minijump SW1. (Refer to Section 6.3.1).
Turn the Mains Isolate Switch ON.
STEP 4 Check that the buzzer sounds and all LEDs on the Operator Display panel
flash for 2 seconds (except Mains On).
STEP 5 Check that the green "MAINS ON" LED indicator is on.
The Controller performs tests on its memory, electronics, and the LCD.
STEP 6 Check that the LCD has good visibility. The LCD displays the FIP PCB
configuration before showing the Base Display.
STEP 7 If doing an E2INIT, set Lk7 to the DATABASE WRITE position, then remove
minijump SW1 and press "ACK" to complete the sequence.
STEP 8 Install and connect the batteries.
Take care not to short the battery leads or connect in reverse polarity when
connecting.
STEP 9 If required, complete programming as per Chapters 6 and 7 and then fit Lk7
on the Controller to the DATABASE PROTECT position.
STEP 10 Perform a Battery Test.
- If this fails check the battery connections, leave for 24 hours and then
retest.
STEP 11 Perform a Bells and System Test (de-isolate all zones first).
A full commissioning test should be carried out as per AS1670.1.