Burnham FM01FD00B Boiler User Manual


 
49
Figure 33: Install 2
nd
Pass Flueway Bafes
Figure 32: Install 3
rd
Pass Flueway Bafes (4 thru 11 Section Boilers Only)
2. On 4 thru 18 Section Boilers - Install four (4) second
pass bafes into second pass ueways until handle
is ush with face of casting as shown in Figure 33,
Detail A.
Lift door high enough to move hinge pockets through
opening in jacket front panel. Engage hinge loop
attached to door over hinge pin attached to block
assembly. Lower door to rest weight on hinge pin
brackets.
 Locate Flueway Bafe Carton(s) marked ‘2FB’ and
‘3FB’ and remove contents. Check Equipment Check
List for proper bafe length and usage per boiler size.
1. On 4 thru 11 Section Boilers - Install four (4) third
pass bafes into third pass ueways until handle is
ush with face of casting as shown in Figure 32,
Detail A.