63
9.5.1 Preparing to perform charging remedy
Remedial apportioning simply apportions the entire
un-apportioned part and calculated the air-conditioning
charge using the normal apportioning data. For remedial
apportioning,
• Settlement-of-accounts term
• Apportioning interval
• Total billing air-conditioning charge
• Failure day watt hour meter integrated value
• Operation data monitoring
must be prepared or performed.
To perform the charging remedy, the items for each assumed case are shown below. V shows that the
remedy is required.
Note:
• This remedial apportioning simply calculates the air-
conditioning charge. It cannot recover to
normal apportioning.
• When the settlement-of-accounts term is one month, the air-
conditioning charge including the
standard charge can be calculated.
• When the operation amount data must be monitored, do it before remedial apportioning.
• This function cannot be used for Without WHM connection proportionally divided electric charge.
Assumed case
Item
att hour
meter failure
(Monitoring
impossible)
HDD failure
(no backup)
HDD failure
(backup)
Computer
crash
System
information
setting error
Remarks
Settlement-of-
accounts term
V V V V V Essential
Remedial
apportioning
interval
V V V V V Essential
Total billing
amount
V V V V V *1
Preparation
Watt hour meter
integrated value
for failure day
(V)
*2
V
Operation amount
data monitoring
V V V See sec.
9.3
Implementation
Remedial
apportioning
V V V V V See sec.
9.5.2
*1 When there is one tariff, preparations are unnecessary.
*2 When replacing a watt hour meter, study the watt hour meter integrated value for the day the failure was
thought to have occurred.
Failure recovery
ó
Failure generation
ê
Settlement-of
accounts day
Settlement-of-
accounts end day
Normal Normal
<Remedial a
pportioning interval>
Settlement-of
accounts term
Normal
apportioning +
Remedial
apportioning
Normal
+ apportioning