58
IMPORTANT
A GAS TIGHTNESS CHECK MUST BE CARRIED OUT IF ANY
GAS CARRYING COMPONENTS HAVE BEEN REMOVED,
REPLACED, OR DISTURBED.
XPAK LPG LABEL
1. Fill in the enclosed LPG label with all the information required
and affix the label as close as possible to existing rating plate
2. Affix the enclosed RED color label over the existing YELLOW
color label under the boiler near to the boiler gas connection.
SEQUENCE OF THE IGNITION SYSTEM
Switch on the boiler as follows:
- Open the gas tap under the boiler by turning it
counterclockwise
- Turn on the general switch of the system and then, after lowering
the flap, turn the function selector to summer
, winter or
winter tank temperature
F
depending on the chosen operating
mode.
The boiler start to run according the automatic sequence: heat
request, fan start-up, tachometer check, ignition trials, gas
opening and ignition start-up.
Fig. 4
Maximum screw
Minimum screw
Compensation
pipe connection