Commissioning
After installation, verify that all components are working properly and that the Module is ready to
begin operation. Before you commission the Module, make sure that the following inspections are
completed:
Initial
Electrical
Mechanical
User interface
After these inspections are complete, the Module is ready for the functional test and charging.
Complete the following procedures to begin operation of the Module:
Functional test
Module charging
After you complete the following two checklists, the Module is ready to begin normal operation:
• Start-up
• Final
Electrical Hazard: Perform Lockout/Tagout procedures on the equipment being
serviced. Failure to remove power before servicing this equipment could result in
serious injury or death.
The initial inspection ensures that the Module has been securely mounted to the floor stand or
sub-base and that the air distribution system is properly installed. The room must be sealed with a
vapor barrier and the Module must be free of damage.
To perform the inspection, see “Initial Inspection Checklist” on page 11.
Caution: Do not run service utilities in front of the blower outlets.
Caution: The vapor barrier minimizes moisture infiltration. Without a vapor barrier, your
equipment will have difficulty maintaining the humidity in the room.
Do not introduce unconditioned outside air into the space.
Note: 914 mm (36 in ) of clear floor space in front of the equipment is required for
service access.
Electrical inspection. The electrical inspection verifies that all electrical connections are secure
and correct and that the Module is properly grounded.