Trane Building Automation System Thermostat User Manual


 
BMTK-SVN01D-EN 23
®
Chapter 3
Termination board wiring
After mounting the termination module, wire the termination board. The
wiring process consists of wiring the termination board to 24 Vac power,
inputs, outputs, and UCMs. This chapter provides information and
procedures that enable you to wire the termination board. Figure 14 on
page 24 shows all field wiring connections.
Refer to the required and optional supply checklists in Appendix A
(Table 15 and Table 16 on page 65) to verify that you have the materials
required to wire the Tracker controller. When termination board wiring is
complete, use the termination module post-installation checklist in
Appendix A (Table 18 on page 70) to verify the wiring.