70 Ceiling & Floor, Ceiling Suspended (50Hz, R22)
15. Installation
Installation of Unit
Unit should be installed for horizontal and vertical dis-
charge application only.
Apply a joint-canvas between the unit and duct to
absorb unnecessary vibration.
Install the unit leaning to a drainage hole side as a fig-
ure for easy water drainage.
A place where the unit will be leveled and that can
support the weight of the unit.
A place where the unit can withstand its vibration.
A place where service can be easily performed.
Select and mark the position for fixing bolts.
Drill the hole for set anchor on the face of ceiling.
Insert the set anchor and washer onto the suspension
bolts for locking the suspension bolts on the ceiling.
Mount the suspension bolts to the set anchor firmly.
Secure the installation plates onto the suspension
bolts (adjust level roughly) using nuts, washers and
spring washers.
Suspension
bolts
Spring
washer
Max.
12mm
Washer
Nut
1 Set anchor
Old building New building
2 Plate washer
3 Spring washer
4 Nut
5 Suspension
bolts
160
320
50
50
A
650
320 160
B
C
CASE 1
POSITION OF SUSPENSION BOLT
CASE 2
POSITION OF CONSOLE BOLT
(Unit:mm)
ABC
Dimension
Model
36k 1350 1255 220
48k, 60k 1750 1655 220
: Tighten the nut and bolt to prevent unit falling
Local supply
Set anchor
Plate washer - M10
Spring washer - M10
Nut - W3/8 or M10
Suspension bolt - W3/8 or M10