START-UP CHECKLIST
(Remove and Store in Job File)
I. PRELIMINARY INFORMATION
MODEL NO.:
DATE:
SERIAL NO.:
TECHNICIAN:
II. PRE-START-UP (insert checkmark in box as each item is completed)
Ⅺ VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
Ⅺ VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
Ⅺ CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
Ⅺ CHECK GAS PIPING FOR LEAKS
Ⅺ CHECK THAT INDOOR (EVAPORATOR) AIR FILTER IS CLEAN AND IN PLACE
Ⅺ VERIFY THAT UNIT INSTALLATION IS LEVEL
Ⅺ CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW
TIGHTNESS
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE L1-L2
L2-L3 L3-L1
COMPRESSOR AMPS L1 L2 L3
COMPRESSOR AMPS L1 L2 L3
INDOOR (EVAPORATOR) FAN AMPS
TEMPERATURES
OUTDOOR (CONDENSER) AIR TEMPERATURE
DB
RETURN-AIR TEMPERATURE
DB WB
COOLING SUPPLY AIR
GAS HEAT SUPPLY AIR
PRESSURES
GAS INLET PRESSURE
IN. WG
GAS MANIFOLD PRESSURE
IN. WG
REFRIGERANT SUCTION
PSIG
REFRIGERANT DISCHARGE
PSIG
Ⅺ VERIFY REFRIGERANT CHARGE USING CHARGING TABLES
Ⅺ VERIFY THAT 3-PHASE SCROLL COMPRESSOR (48SS048,060 AND 48SX036-060 UNITS) ROTATING IN
CORRECT DIRECTION
----------------------------------------------------------------------------------------
CUT ALONG DOTTED LINE CUT ALONG DOTTED LINE
Copyright 1998 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 1 4
Tab 1a 6a
PC 111 Catalog No. 534-721 Printed in U.S.A. Form 48SS,SX-12SI Pg CL-1 9-98 Replaces: 48SS,SX-11SI