Installation
16 CAH-SVX01A-EN
TCP Base to Interior Wall
Section Assembly (Typical)
Note: Failure to completely
compress the gasketing may result
in air leakage.
1 Join the two units and secure
with field provided 5/8-inch flat
washers and 5/8-inch X 2-1/2-inch
grade 9 bolts though each of the
six holes.
Figure 8. TCP base to interior wall sections
4" X 1/4" GASKET
SECURE 2" X 2" ANGLE TO WALL
W/#14 S.M. SCREWS @ 12" CTR'S
INTERIOR
WALL
SPLIT
CAULK
CAULK
SPLIT
SPLIT
INTERIOR
WALL
SPLIT
BASE TO WALL ASSEMBLY COMPLETE
CAULK
2 Apply caulk the length of the
base between the 2-inch X 2-inch
angle on the one base section
and the wall on the adjoining
section. See Illustration below.
Note: Use a polyurethane or
equivalent caulk.
3 Secure the 2-inch X 2-inch angle
to the adjoining wall with
number 14 sheet-metal crews on
12-inch centers along the length
of the angle and wall.