Performance Tests
Performance Verification Procedures
Procedure:
1.
Install the test hookup and preset the instrument controls (see Fig-
ure 1-5):
HI
LO
Output Sense
DC Calibrator
50
Coaxial Cables
Dual Banana to
BNC Adapters
BNC T
Connector
Figure 1-5: Initial Test Hookup
a.
Hook up the test-signal source:
Set the output of a DC calibration generator to 0 volts.
Connect the output of a DC calibration generator through a
dual-banana connector followed by a 50 precision coaxial cable
to one side of a BNC T connector.
Connect the Sense output of the generator through a second
dual-banana connector followed by a 50 precision coaxial cable
to the other side of the BNC T connector. Now connect the
BNC T connector to CH 1.
b.
Initialize the oscilloscope:
Press save/recall SETUP.
Press the main-menu button Recall Factory Setup.
Press the side-menu button OK Confirm Factory Init.
c.
Modify the default settings:
Press SHIFT; then ACQUIRE MENU.
Press the main-menu button Mode; then press the side-menu
button Average 16.
Press CURSOR.
Press the main-menu button Function; then press the side-menu
button H Bars.
Press DISPLAY.