To replace the  rst starter elbow with two 45° elbows,
refer to Figure 7.4. All other 90° elbows can be replaced
with two 45° elbows.
General Rules:
SUBTRACT 3 ft. from the total H measurement for each
90° elbow installed horizontally.
SUBTRACT 1-1/2 ft. from the total H measurement for
each 45° elbow installed horizontally.
A maximum of three 90° elbows (or six 45° elbows)
may be used in any vent con guration. Some elbows
may be installed horizontally. See Figure 7.9.
Elbows may be placed back to back anywhere in the
system as long as the  rst 90° elbow is a starter elbow
except as shown in Figure 7.4.
When penetrating a combustible wall, a wall shield
restop must be installed.
When penetrating a combustible ceiling, a ceiling
restop must be installed.
Horizontal runs of vent do not require vertical rise;
horizontal runs may be level.
E. Vent Diagrams
Figure 7.3
One Elbow
1. Top Vent - Horizontal Termination
V1 Min. V1 Max. H1 Max.
3 ft (.91 m) - 1.5 ft (.46 m)
4 ft (1.22 m) - 6 ft (1.83 m)
5 ft (1.52) - 11 ft (3.35 m)
6 ft (1.83 m) - 13 ft (3.96 m)
7 ft (2.13 m) - 15 ft (4.57 m)
10 ft (3.05 m) 25 ft (7.62 m) 20 ft (6.10 m)