Quadra-Fire QFP44 Stove User Manual


 
Quadra-Fire • QFP44 • 4051-300 Rev M • 09/08 25
Combustible flooring may be installed
next to the front of the appliance.
ALL SURFACES MUST BE FLUSH
WITH THE BOTTOM OF THE UNIT.
C
B
A
Drywall
1-1/2 in.
(38 mm)
0 in.
1-1/2 in.
(38 mm)
0 in.
D
40-7/8 in.
(1038 mm)
to ceiling
0 in. to level
of standoffs
36 in.
(914 mm)
Combustible Object
1-1/2 in.
(38 mm)
B. Construct the Appliance Chase
A chase is a vertical box-like structure built to enclose the
gas appliance and/or its vent system. In cooler climates
the vent should enclosed inside the chase.
NOTICE:
Treatment of ceiling ¿ restops and wall shield
¿ restops and construction of the chase may vary with the
type of building. These instructions are not substitutes for the
requirements of local building codes. Therefore, you MUST
check local building codes to determine the requirements
to these steps.
Chases should be constructed in the manner of all out-
side walls of the home to prevent cold air drafting prob-
lems. The chase should not break the outside building
envelope in any manner.
Walls, ceiling, base plate and cantilever  oor of the chase
should be insulated. Vapor and air in ltration barriers
should be installed in the chase as per regional codes for
the rest of the home. Additionally, in regions where cold
air in ltration may be an issue, the inside surfaces may
be sheetrocked and taped for maximum air tightness.
Figure 5.2 Clearances to Combustibles
C. Clearances
NOTICE: Install appliance on hard metal or wood surfaces
extending full width and depth. DO NOT install directly on
carpeting, vinyl, tile or any combustible material other than
wood.
WARNING! Risk of Fire! Maintain speci¿ ed air space
clearances to appliance and vent pipe:
Insulation and other materials must be secured to
prevent accidental contact.
The chase must be properly blocked to prevent blown
insulation or other combustibles from entering and
making contact with  replace or chimney.
Failure to maintain airspace may cause overheating and
a  re.
To further prevent drafts, the wall shield and ceiling  re-
stops should be caulked with high temperature caulk to
seal gaps. Gas line holes and other openings should be
caulked with high temp caulk or stuffed with unfaced insu-
lation. If the appliance is being installed on a cement slab,
a layer of plywood may be placed underneath to prevent
conducting cold up into the room.
Note: If the inside of the framed cavity is to be  nished, the
framing dimensions must include the  nished surface. If
drywall is to be attached to the rear wall, the depth must be
measured from the drywall surface.
Model
A
Rough Opening
(Width)
B
Rough Opening
(Height)
C
Rough Opening
(Depth)
D
Rough Opening
(DVP Pipe)
QFP44
inches 52 66 5/8 31 10
mm 1321 1692 787 254