Heat & Glo • 6000TRS-CE • 2049-900 Rev. Q • 2/1130
Figure 28
The gas line should be
installed by a qualifi ed
service technician.
!
Note: Have the gas supply line installed by a
qualifi ed service technician in accordance with
all building regulations.
Note: Before the fi rst fi ring of the fi replace, the gas
supply
line should be purged of any trapped air.
NOTE: Consult local building regulations to
properly size the gas supply line leading to the
(Rp 1/2”) hook-up at the unit.
This gas inlet connection is ISO 7-Rp 1/2 (BSP Rp
1/2).
To install the gas supply line:
• When attaching the pipe, support the control so that
the lines are not bent or torn.
• After the gas line installation is complete, use a soap
solution to carefully check all gas connections for
leaks.
Step 6
The Gas
Supply Line
WARNING: DO NOT USE AN OPEN FLAME
TO CHECK FOR GAS LEAKS.
• At the gas line access hole, use insulation to repack
the space around the gas pipe.
• Insert insulation from the outside of the fi replace and
pack the insulation tightly to totally seal between
the pipe and the outer casing.
GAS LINE
ACCESS