Emerson MINI-MATE2 Fan User Manual


 
Site Preparation and Installation
Liebert
®
Mini-Mate2
38
5.9 Checklist for Completed Installation
___ 1. Proper clearance for service access has been maintained around the equipment.
___ 2. Equipment is level and mounting fasteners are tight.
___ 3. Piping completed to refrigerant or coolant loop (if required). Refrigerant charge added (if
required).
___ 4. Condensate pump installed (if required).
___ 5. Drain line(s) connected and checked for leaks.
___ 6. Water supply line connected to humidifier (if required). Route to allow air filter removal.
___ 7. Field provided drain pan with drain installed under all cooling units and ceiling-mounted
water/glycol condensing units.
___ 8. Filter box installed.
___ 9. Ducting completed.
___ 10. Filter(s) installed in return air duct.
___ 11. Line voltage to power wiring matches equipment serial tag.
___ 12. Power wiring connections completed between disconnect switch, evaporator and condensing
unit, including earth ground.
___ 13. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 14. Control wiring connections completed to evaporator and condensing unit (if required,
including wiring to wall-mounted control panel and optional controls).
___ 15. Control panel DIP switches set based on customer requirements.
___ 16. All wiring connections are tight.
___ 17. Foreign materials have been removed from in and around all equipment installed (shipping
materials, construction materials, tools, etc.)
___ 18. Fans and blowers rotate freely without unusual noise.
___ 19. Inspect all piping connections for leaks during initial operations. Correct as needed.
___ 20. Rubber band is removed from evaporator condensate pan float switch.