Quadra-Fire 7100FP-BK-B Indoor Fireplace User Manual


 
September 7, 2007
433-1390D
Page 33
7100FP EPA Woodburning Fireplace
R
This kit is tested and safe when installed in accordance with
this installation manual. It is your responsibility to read all
instructions before starting installation and to follow these
instructions carefully during installations.
Installation of this kit MUST by performed by a quali ed ser-
vice technician.
The Heat-Zone-Wood kit is carefully engineered and must
be installed only as speci ed. If you modify it or any of its
components you will void the warranty and you may possibly
cause a re hazard. Installation must be done according to
applicable local, state, provincial and/or national codes.
Plan the location of the replace and warm air duct run(s).
D. Heat Zone Kit
Ceiling Register
Wall Register
Floor Register
Two Duct Kits
Ceiling Register
12 in. (305mm) minimum clearance
from register to ceiling
Possible Air Duct Runs / Locations
DUCT RUN REQUIREMENTS
MAXIMUM Duct Run = 40 ft. (12m)
MINIMUM Duct Run = 36 in. (914mm)
DUCTING MATERIAL
6 in. (152mm) B-Vent Only
DO NOT DUCT into existing furnace plenum
MINIMUM CLEARANCE TO COMBUSTIBLES
1 in. (25mm) from the B-Vent
1
/2 in. (13mm) from top & bottom of outlet box
0 in. (0mm) from the sides of outlet box
12 in. (305mm) from wall register to ceiling*
*(See Figure 33.1).
CAUTION
ALL wiring should be done by a quali ed electrician and
shall be in compliance with local codes and with the National
Electric Code NFPA/NEC No. 70-current (in the United
States), or with the current CSC22.1 Canadian Electric
Code (in Canada).
Figure 33.1 Minimum Clearances to Combustibles