TESTING YES/NO
DATE TO BE
COMPLETED
1. The cooling tower fan has been checked for blade pitch and
proper operation.
2. The chilled water and condenser water lines have been:
a. Filled
b. Tested
c. Flushed
d. Vented
e. Strainers cleaned
3. The chilled water and condenser water pumps have been
checked for proper rotation and flow.
4. The following cooling load will be available for start-up:
a. 25%
b. 50%
c. 75%
d. 100%
5. The refrigerant charge is at the machine.
6. Services such as electrical power and control air will be avail-
able at start-up.
7. The electrical and mechanical representatives will be available
to assist in commissioning the machine.
8. The customer’s operators will be available to receive instruc-
tions for proper operation of the chiller after start-up.
Concerns about the installation/request for additional assistance:
I am aware that the start-up time for a Carrier chiller can take between 2 and 6 days depending on the model of the machine and
the options and accessories used with it.
Your contact at the jobsite will be
Phone number
Beeper number
Fax number
In accordance with our contract, we hereby request the services of your technician to render start-up services per contract terms
for this job on (Date). I understand that the technician’s time will be charged as extra services due to correcting items
in this checklist that are incomplete.
Signature of Purchaser
Signature of Jobsite Supervisor
----------------------------------------------------------------------------------------
CUT ALONG DOTTED LINE CUT ALONG DOTTED LINE
Copyright 1997 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 2
Tab 5a
PC 211 Catalog No. 531-940 Printed in U.S.A. Form 19XR-2SI Pg CL-2 10-97 Replaces: 19XR-1SI