Amana AMV9 Furnace User Manual


 
28
FILTER
AIR FLOW
CENTRAL
RETURN
GRILLE
FILTE R
SIDE RETURN
EXTERNAL FILTER
RACK KIT
(EITHER SIDE)
FIL
T
ER
FILTER
A
IR FLOW
FILTER
ACCESS
DOOR
CENTRAL
RETURN
GRILLE
RETURN
DUCT
F
I
LTER
FILTER
SUPPORT
BRACKET
(PROVIDED)
Possible Upright Upflow Possible Upright
Counterflow
Filter Locations
NOTE: Internal filter retention is not provided on this furnace. If an
internal installation is desired, an internal filter retention kit is avail-
able as an accessory. Please see your distributor for details.
HORIZONTAL INSTALLATIONS
Filters must be installed in either the central return register or in the
return air duct work.
XIVXIV
XIVXIV
XIV
. ST. ST
. ST. ST
. ST
ARAR
ARAR
AR
TUP PRTUP PR
TUP PRTUP PR
TUP PR
OCEDURE & ADOCEDURE & AD
OCEDURE & ADOCEDURE & AD
OCEDURE & AD
JUSTJUST
JUSTJUST
JUST
MENTMENT
MENTMENT
MENT
Furnace must have a 115 VAC power supply properly connected
and grounded. Proper polarity must be maintained for correct op-
eration. In addition to the following start-up and adjustment items,
refer to further information in Section XVI, Operational Checks.
HEAT A NTICIPATOR S ETTING
The heat anticipator in the room thermostat must be correctly ad-
justed to obtain the proper number of cycles per hour and to pre-
vent “overshooting” of the setting. Set the heat anticipator setting to
0.7 amps. Follow the thermostat manufacturer’s instructions on
how to adjust the heat anticipator setting.
DRAIN TRAP PRIMING
The drain trap must be primed prior to furnace startup. To prime, fill
the drain trap with water. This ensures proper furnace drainage
upon startup and prohibits the possibility of flue gases escaping
through the drain system.
FURNACE OPERATION
Purge gas lines of air prior to startup. Be sure not purge lines into
an enclosed burner compartment.
Check for leaks using an approved chloride-free soap and water
solution, an electronic combustible gas detector, or other approved
method. Verify that all required kits (propane gas, high altitude,
etc.) have been appropriately installed.
FURNACE STARTUP
1. Close the manual gas shutoff valve external to the furnace.
2. Turn off the electrical power to the furnace.
3. Set the room thermostat to the lowest possible setting.
4. Remove the burner compartment door.
NOTE: This furnace is equipped with an ignition device which
automatically lights the burner. Do not try to light the burner by
hand.
5. Move the furnace gas valve manual control to the OFF
position.
6. Wait five minutes then smell for gas. Be sure check near
the floor as some types of gas are heavier than air.
7. If you smell gas after five minutes, immediately follow the
instructions on page 4 of this manual. If you do not smell
gas after five minutes, move the furnace gas valve manual
control to the ON position.
8. Replace the burner compartment door.
9. Open the manual gas shutoff valve external to the furnace.
10. Turn on the electrical power to the furnace.
11. Adjust the thermostat to a setting above room temperature.
12. After the burners are lit, set the thermostat to desired
temperature.
FURNACE SHUTDOWN
1. Set the thermostat to the lowest setting.
The integrated control will close the gas valve and extinguish
flame. Following a 15 second delay, the induced draft blower
will be de-energized. After a 120, 150, 180 or 210-second
delay period (field selectable delay OFF [90, 120, 150, 180]
plus 30-second ramp down), the circulator blower de-
energizes.
2. Remove the burner compartment door and move the furnace
gas valve manual control to the OFF position.
3. Close the manual gas shutoff valve external to the furnace.
4. Replace the burner compartment door.
GAS SUPPLY PRESSURE MEASUREMENT
CAUTION
T
O PREVENT UNRELIABLE OPERATION OR EQUIPMENT DAMAGE, THE INLET
GAS SUPPLY PRESSURE MUST BE AS SPECIFIED ON THE UNIT RATING PLATE
WITH ALL OTHER HOUSEHOLD GAS FIRED APPLIANCES OPERATING.
WHITE-RODGERS 36G54 GAS VALVE
The line pressure supplied to the gas valve must be within the
range specified below. The supply pressure can be measured at
the gas valve inlet pressure boss or at a hose fitting installed in the
gas piping drip leg. The supply pressure must be measured with
the burners operating. To measure the gas supply pressure, use
the following procedure.
On/Off Switch
Inlet
Pressure Boss
High Fire
Coil Terminal (HI)
Low Fire
Regulator Adjust
M
a
n
o
m
e
t
e
r
M
a
n
o
m
e
t
e
r
H
o
s
e
A
High Fire Regulator
Adjust
Regulator
Vent
Common
Terminal (C)
Coaxial Coil
Terminal (M)
Outlet
Pressure Boss
Open to
Atmosphere
White-Rodgers Model 36G54 Connected to Manometer