B. Assemble Slip Sections
Slide the inner ue of the slip section into the inner ue of
the pipe section and the outer ue of the slip section over
the outer ue of the pipe section. See Figure 10.6.
• Slide together to the desired length.
Figure 10.6 Slip Section Pilot Holes
Figure 10.7 Screws into Slip Section
Pilot hole
Pilot hole
Continue adding pipe as necessary following instructions
in “Assembling Pipe Sections.”
NOTICE: If slip section is too long, the inner and outer ues
of the slip section can be cut to the desired length.
• Maintain a 1-1/2 in. (38 mm) overlap between the slip
section and the pipe section.
• Secure the pipe and slip section with two screws no
longer than 1/2 in. (13 mm), using the pilot holes in the
slip section. See Figure 10.7.
120º
Figure 10.8 Securing Vertical Pipe Sections
120º
Figure 10.9 Securing Horizontal Pipe Sections
C. Secure the Vent Sections
• Vertical runs of DVP pipe must be supported every 8 ft.
(2.44 m) after the 25 ft. (7.62 m) maximum unsupported
rise.
• Vertical runs of SLP pipe must be supported every 8 ft.
(2.44 m).
• Horizontal sections must be supported every 5 feet
(1.52 m).
• Vent supports or plumbers strap (spaced 120º apart)
may be used to support vent sections. See Figures 10.8
and 10.9.
• Wall shield restops may be used to provide horizontal
support vent sections.
• SLP ceiling restops have tabs that may be used to
provide vertical support.
WARNING! Risk of Fire, Explosion or Asphyxiation!
Improper support may allow vent to sag and separate.
Use vent run supports and connect vent sections per in-
stallation instructions. DO NOT allow vent to sag below
connection point to appliance.