3. If not already completed, install gas piping to
replace location. This installation includes an
approved exible gas line (if allowed by local
codes) after the equipment shutoff valve. The
exible gas line must be the last item installed
on the gas piping. See Installing Gas Piping
to Fireplace Location, page 17.
4. Carefully set replace in front of rough opening
with back of replace inside wall opening.
5. Attach exible gas line to gas supply. See Con-
necting Fireplace to Gas Supply, page 18.
6. Plug electrical cord(s) into electrical outlet
installed in step 2.
7. Carefully insert replace into rough opening.
8. Attach replace to wall studs using nails or
wood screws through holes in nailing ange
(see Figure 36).
9. Check all gas connections for leaks. See
Checking Gas Connections, page 19.
10. Install brass trim. See Assembling and Attach-
ing Optional Brass Trim, page 23
INSTALLATION
Continued
35
1
/
2
"
17
3
/
4
"
33"
39
3
/
8
"
27
7
/
8
"
55
5
/
8
"
35
1
/
2
"
Figure 34 - Rough Opening for Installing
in Wall
Figure 35 - Rough Opening for Installing
in Corner
Figure 36 - Attaching Fireplace to Wall
Studs
Nailing
Flanges
Nails or
Wood
Screws

Installation
If placing mantel above built-in replace, you must
meet minimum clearance between mantel shelf and
top of replace opening.

    
   
    
    

   
   
   
minimum clearances shown in

NOTICE: If your installation does
not meet the minimum clear-
ances shown, you must do one

• raise the mantel shelf to an

• remove the mantel shelf