Note: When constructing the framed opening, please ensure
there is access to install the gas lines when the unit is installed.
See diagram 3 for details.
2) For exterior walls, insulate the enclosure to the same degree as the rest
of the house, apply vapour barrier and drywall, as per local installation
codes. (Do not insulate the replace itself.)
3) The unit does not have to be completely enclosed in a chase. You
must maintain clearances from the vent to combustible materials: See
"Clearances" section. Combustible materials can be laid against the
side and back standoffs and the stove base.
4) Finishing material such as tile, river rock, etc. must not pertrude beyond
the front facing anges on all 4 sides of the rebox opening.
FRAMING & FINISHING
Diagram 2
Diagram 3
NON-COMBUSTIBLE REQUIREMENTS
IMPORTANT
If converting this unit to LP, it is highly recommened
the conversion be done BEFORE the unit is slid into
position for ease of conversion. See "Conversion
from NG to LP" section for instructions.
Diagram 1
1) Frame in the enclosure for the unit with framing material. The framed
opening for the assembled kit is 45-7/8" high x 43" wide x 25-3/4"
deep (1143mm x H 1092mm W x 654mm D). See Diagram 1. Also
see Diagram 2 for corner installations. All other framing may be of
IMPORTANT: Header must be metal stud. All other framing may