It is important to maintain the required clear-
ances to combustibles: 1" (25 mm) at all sides
for all vertical runs; and 3" (76 mm) at the top,
1" (25 mm) at sides, and 1" (25 mm) at the
bottom for all horizontal/inclined runs.
H. Frame roof opening - Identify location for
vent at the roof. Cut and/or frame opening per
Roof Framing Chart and
Figure 19.
Figure 20
Figure 19
Figure 22
Figure 21
If the vent system extends more than 5' (1.5
m) above the roof flashing, stabilizers may be
necessary. Additional screws may be used at
section joints for added stability. Guide wires
may be attached to the joint for additional sup-
port on multiple joint configurations.
Framing Dimensions for Roof
Inches (millimeters)
Pitch C D
0/12 10-1/2 in.
(267 mm)
10-1/2 in.
(267 mm)
6/12 10-1/2 in.
(267 mm)
12 in.
(305 mm)
12/12 10-1/2 in.
(267 mm)
17 3/4 in.
(451 mm)
C
D
Storm
Collar
Flashing
K. Install the vertical termination - The final
step involves installation of the SV4.5CGV-1
Vertical Termination. Extend the vent sections
to the height as shown in the "Vertical vent ter
-
mination section" on Page 7. The SV4.5CGV-1
Vertical Termination (Figure 22) installs in the
exact same fashion as any other Secure Vent
section. Align the termination over the end of
the previously installed section, adjusting the
radial alignment until the four locking dimples
of the termination are aligned with the inlets of
the four incline channels of the last vent section.
Push the termination down until it fully engages,
then twist the termination clockwise running the
dimples down and along the incline channels
until they seat at the end of the channels.
I. Install the roof flashing - Extend the vent
sections through the roof structure. Install the
roof flashing over the vent section and posi-
tion such that the vent column rises vertically
(use carpenters level) (Figure 20). Nail along
perimeter to secure flashing or adjust roofing
to overlap the flashing edges at top and sides
only and trim where necessary. Seal the top
and both sides of the flashing with waterproof
caulking.
J. Install the storm collar - Install the storm
collar, supplied with the flashing, over the
vent/flashing joint. See Figure 21. Loosen
the storm collar screw. Slide collar down until
it meets the top of the flashing. Tighten the ad-
justing screw. Apply non-combustible caulking
or mastic around the circumference of the joint
to provide a water tight seal.