NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.
25
Step 4. FIELD WIRING
Note: The gas valve is set in place and pre-wired
at the factory.
A. SIT and Honeywell Millivolt Wiring
(See Figure 46)
1. Select any of the following optional controls:
unit-mounted burner OFF/ON switch (rocker
switch), wall-mounted switch or the remote
control kit. If unit-mounted ON/OFF control is
selected mount it in the gas valve mounting
bracket.
2. If wall-mounted ON/OFF control is selected
mount it in a convenient location on a wall
near the fireplace.
3. Wire the control within the millivolt control
circuit using the 15 feet of 2 conductor wire
supplied with the unit . Caution: do not
connect the optional wall switch to a 120V
power supply.
4. Alternatively, the appliance may be operated
without the use of the controls indicated in
step 1, solely by manipulating the gas valve
control knob. In order to use this method,
twist the free ends of the two conductor wire
(which would otherwise go to the standard
ON/OFF switch or Optional Switch) together
as shown in Figure 46. Note: Wire is located
inside the control compartment
Note: The supplied 15 feet of 2 conductor wire
has one end of each conductor connected to
the gas valve circuit and the other end of each
conductor placed loose inside the control
compartment.
Figure 46- Millivolt Wiring Diagram
Field Wired
Factory
Wired
TH
TP
TH
TP
* Optional
Burner Switch
Thermopile
Standard OFF/ON
Switch
Schematic
Representation
Only
• If any of the original wire as supplied must be replaced, it must be replaced with
Type AWM 105 C - 18 gage wire.
* Optional Kits Installed - OFF/ON wall switch, wall thermostat or remote control receiver.
FORCED AIR BLOWER (FBK-100 provided)
(See Figure 47) -
The blower and blower ON/Off control switch
are factory installed. An electrical outlet box is
also factory installed for the connection of the
electrical power supply to the blower.
1. Route a 3-wire, 120Vac 60Hz 1ph power
line to the lower right rear corner of the
appliance.
2. Connect the black supply wire to the top
outlet's black pigtail lead and to the switch's
black lead. Connect the white supply wire to
the neutral terminal of the outlet box.
3. Connect the ground supply wire to the outlet
box green ground screw as shown.
4. Plug the blower cord into the bottom recep-
tacle of the outlet box.
HT
PT
HT
PT
*
* Twist wires together to operate unit
solely by manipulating the gas valve
control knob; or connect wires to
optional on/off switch or wall switch
or thermostat or remote control to
operate unit.
Figure 47 - Blower Wiring Diagram
1. If any of the original wire as supplied must be replaced,
1. it must be replaced with Type AWM 105°C – 18 GA. wire.
2. 120V, 60Hz – Less than 3 amps.
Wiring Diagram
Showing the Blower Wiring
for the Optional FBK-100 Kit
Factory Wired
Field Wired
Schematic Representation Only
Junction Box
Tab Intact
Tab
Broken
Plug blower
into this
receptacle
n
e
erG
- dnuor
G
*Optional Accessory Switch
Optional
Blower
Ground
etihW - lartueN
120 VAC - Black
Green
Ground
Screw
White
Green
Neutral
Side of
Receptacle
Hot
Side of
Receptacle
Red
Black
*J-BOX WIRING FOR
OPTIONAL (BLOWER
CONTROL) ACCESSORY
SWITCH
�
�
u
CAUTION: Label all wires prior to disconnec-
tion when servicing controls. Wiring errors can
cause improper and dangerous operation.
ATTENTION: Au moment de l'entretien des
commandes, étiquetez tous les fils avant de
les débrancher. Des erreurs de cáblage peu-
vent entraîner un fonctionnement inadéquat
et dangereux.
Verify proper operation after servicing.
S'assurer que l'appareil fonctionne adé-
quatement une fois l'entretien terminé.
CAUTION
Ground supply lead must be con-
nected to the wire attached to the
green ground screw located on the
outlet box. See Figure 47. Failure to
do so will result in a potential safety
hazard. The appliance must be
electrically grounded in accordance
with local codes or, in the absence of
local codes, the National Electrical
Code, ANSI/NFPA 70-latest edition.
(In Canada, the current CSA C22-1
Canadian Electrical Code).