Ariston 47-116-17 Boiler User Manual


 
9
275
Refer to the illustrations in section 2.10.1.
1. Unscrew the screws “A” and rotate the control panel forwards.
2. Insert the connecting cable of the under floor heating sensor into
the cable gland “B” and open the lid of the instrument panel
after having unscrewed the fastening screws “C”.
3. Remove a blind grommet, make a hole in it and insert the
connecting cable of the under floor heating sensor through it.
4. Remove the jumper located in the flying clamp
5. Connect the cables of the under floor heating sensor to the flying
clamp connected to position C6 on the P.C.B. (in place of the
position previously occupied by the jumper).
6. Bring the grommet back to its initial position, close the lid and
lastly the control panel.
2.10.4. UNDER FLOOR HEATING CONNECTION
2.10.5. REMOTE CONTROL TERMINAL BLOCK,
CYLINDER PROBE AND SECONDARY OUTLET
C5 (1-2)
(red)
C6 (3-11)
(grey)
C7 (1-9)
(violet)
CONNECTIONS TO THE P.CB.
JUMPER:
UNDER FLOOR
HEATING
SENSOR
REMOTE CONTROL
SECONDARY OUTLET
(LPG valve,
secondary pump)
2.10.3. ACCESSORY CONNECTION TERMINAL BLOCK
2.10.2. REMOTE
CONTROL CONNECTION
Refer to the illustrations in section 2.10.1.
1. Unscrew the screws “A” and rotate the control panel forwards.
2. Insert the connecting cables of the remote control into the cable
gland “B” and open the lid of the control panel after having
unscrewed the fastening screws “C”.
3. Remove a blind grommet, make a hole in it and pass the
connecting cable of the remote control through it.
4. Connect the cables of the remote control to the flying lead (see
section 2.11.) connected to position C5 on the P.C.B. (positions
with no closed jumper).
5. Bring the grommet back to its initial position, then close the lid
and lastly the control panel.
N
OTE
: The wiring of the RC must be done by using 2 x 0.5 mm
2
cable
this guarantees a maximum length of 500 m.
The “BUS” cable of the RC must be wired separately from the 230
VAC cable.
NOTE: The wiring of the Outdoor Sensor (SE) must be done by using
2 x 0.5 mm
2
cable this guarantees a maximum length of 50 m.
The sensor must be positioned at least 2 - 2.5 m above the
ground and where possible facing north. The sensor must not
be exposed to direct sunlight.