The installation must conform to the requirements of the
authority having jurisdiction or, in the absence of such
requirements, to the National Fuel Gas Code, ANSI Z223.1-
latest edition.
This installation must also conform to the additional require-
m
ents in this Slant/Fin Instruction Book.
BOILER LOCATION
Provide a level, solid foundation for the boiler. Location
should be as near as possible to chimney or outside wall so
that the flue pipe from boiler is short and direct. (See para-
graph heading “Vent Termination Location and Clearance” on
page 8.) The location should also be such that all boiler
components are protected from water (dripping, spraying,
rain, etc.) during appliance operation and service (circulator
replacement, control replacement, etc.).
BOILER FOUNDATION
A.
Provide a solid, level foundation, capable of supporting the
weight of the boiler filled with water, and extending at least
2" past the jacket on all sides. See dimensions of boilers,
page 2.
B. Boiler can be installed on both combustible and
non-combustible floors, but must NOT be installed on or
above carpeting.
C. If boiler is to be located over buried conduit containing
electric wires or telephone cables, consult local codes or
the National Board of Fire Underwriters for specific
requirements.
MINIMUM CLEARANCES FROM COMBUSTIBLE
CONSTRUCTIONS
A
. Minimum clearances to the exterior surfaces of the boiler
shall be as follows:
M
INIMUM ALCOVE AND CLOSET CLEARANCE
F
or Combustible Recommended
Surf
ace Construction for Service
F
ront 0" 24"
Rear 0" 6"
Left Side 0" 0"
Right Side 0" 0"
T
op 4" 6"
Flue Connector:
Enclosed — 2" 6"
Uninclosed — 1" 6"
B. Provide accessibility clearance of 8" on sides requiring
servicing and 18" on sides used for passage.
C. All minimum clearances shown above must be met. This
may result in increased values of some minimum clear-
ances in order to maintain the minimum clearances of
others.
D. Clearance from hot water pipes shall be 1 inch**.
** A
t points where hot water pipes emerge from a floor,
wall or ceiling,
the clearance at the opening through the finished floor boards or wall
or ceiling boards may be not less than 1/2 inch. Each such opening
shall be covered with a plate of uncombustible material.
Figure 3. Jaguar boiler min. clearances for combustible
construction.
INSTALLATION REQUIREMENTS
* 2" FOR ENCLOSED
SAFETY
KEEP THE BOILER AREA CLEAR AND FREE FROM
COMBUSTIBLE MATERIALS, GASOLINE AND OTHER
FLAMMABLE VAPORS AND LIQUIDS.