Finishing
A. FramingandFinishingInstructions
WARNING! Risk of Fire! Comply with all minimum clear-
ances to combustibles as specied. Framing closer than the
minimums listed must be constructed entirely of noncom-
bustible materials (i.e., steel studs, concrete board, etc.)
FinishingInstructions
It is important to follow the framing and nishing instruc-
tions to ensure proper placement of replace into the sur-
rounding framing/nishing materials.
Wall sheathing materials 1.3 cm thick are specied in
this installation manual to properly align with the factory-
installed non combustible material.
WARNING! Risk of Fire! DO NOT remove the factory-
installed non-combustible board or cover it with combus-
tible material, such as:
• Drywall (gypsum board)
• Plywood
• Materials that do not meet the ASTM E 136 Non-com-
bustibility standard (below).
Removal of factory-installed, non-combustible board and/
or use of materials not meeting the ASTM E 136 standard
may cause re.
Non-CombustibleMaterialsSpecication
Material which will not ignite and burn. Such materials are
those consisting entirely of steel, iron, brick, tile, concrete,
slate, glass or plasters, or any combination thereof.
Materials that are reported as passing ASTM E 136,
StandardTestMethodforBehaviorofMaterialsina
Vertical Tube Furnace at 750ºC and UL763 shall be
considered non-combustible materials.
SettingtheFireplaceintotheFraming
Unlike many traditional, single-sided Heat & Glo replaces,
this replace is recessed into surround framing. The left
and right nailing tabs were designed so the replace
is recessed to the correct location within the framing
materials.
1. Bend two nailing tabs away from replace 180 degrees
on both left and right nailing tabs. See Figure 13.1.
2. Screw each nailing tab to the adjoining framing
material. Ensure that the air space clearance is
maintained on the sides of the replace. See Figure
13.2.
Figure13.1NailingTabsInstallationPosition
NAILING
TABS
FACTORY-INSTALLED
NON-COMBUSTIBLE BOARD
Figure13.2FrontSideFinishingDetail
1 IN.
FRAMING
1/2 IN. FACTORY-SUPPLIED
NON-COMBUSTIBLE BOARD
NAILING TAB