GAS-FIRED BOILER Boiler Manual
Figure 7-13
Figure 7-14
K. DIAGRAMS FOR VERTICAL VENTING
10'-0" MIN.
WHICHEVER IS GREATER
12" OVER MAXIMUM
SNOW LEVEL OR 24"
AND COUPLING (EXHAUST)
EXTERIOR WALLRIGHT SIDE VIEW
ROOF VENT WITH TEE (INTAKE)
EXHAUST
VENT
AND VERTICAL PIPING
ALL HORIZONTAL
COUPLING
TEE
STRAIGHT
SUPPORT BRACKETS
MUST BE USED ON
INTAKE AIR
VENT
24" MIN.
WHICHEVER IS GREATER
12" OVER MAXIMUM
SNOW LEVEL OR 24"
10'-0" MIN.
ROOF VENT WITH TEE (INTAKE)
VIEW
EXHAUST VENT
COUPLING)
(STRAIGHT
AND COUPLING (EXHAUST)
MUST BE USED ON
ALL HORIZONTAL
AND VERTICAL PIPING
SUPPORT BRACKETS
INTAKE AIR
VENT
(TEE)
RIGHT SIDE
EXTERIOR WALL
24" MIN.
WHICHER IS GREATER
12" OVER MAXIMUM
SNOW LEVEL OR 24"
10'-0" MIN.
RIGHT SIDE VIEW
EXTERIOR WALL
INTAKE AIR
VENT
ROOF VENT WITH
CONCENTRIC VENT KIT
AND VERTICAL PIPING
ALL HORIZONTAL
SUPPORT BRACKETS
MUST BE USED ON
EXHAUST
VENT
WHICHEVER IS GREATER
12" OVER MAXIMUM
SNOW LEVEL OR 24"
10'-0" MIN.
VIEW
RIGHT SIDE
ROOF VENT WITH
CONCENTRIC VENT KIT
SUPPORT BRACKETS
MUST BE USED ON
ALL HORIZONTAL
AND VERTICAL PIPING
EXTERIOR WALL
GENERAL NOTE: All vent pipes must be glued, properly supported and the exhaust must be pitched a
minimum of a ¼" per foot back to the heater (to allow drainage of condensate).
NOTE: When placing support brackets on vent piping, the first bracket must be within 1 foot of the
appliance and the balance at 4 foot invervals on the vent pipe. The boiler venting must be readily
accessible for visual inspection for the first three feet from the boiler.