www.desatech.com
113110-01H 11
26
7
/
8
"
26
7
/
8
"
3/4" Off
The Floo
r
Minimum
10
1
/
2
"
Figure 7 - Rough Opening for Installing
in Wall
36
5
/
8
"
25
7
/
8
"
51
3
/
4
"
26
7
/
8
"
Figure 8 - Rough Opening for Installing
in Corner
INSTALLATION
Continued
Note: If not installing blower accessory,
you may wish to run electrical wiring to
your replace for future blower installation
(see Accessories, page 35). Use only ap-
proved three-wire electrical wiring.
Note: A qualied installer should make all
electrical connections.
-
-
cal outlet is included with the
-
3. Install gas piping to replace location. This
installation includes an approved exible
gas line (if allowed by local codes) after
the equipment shutoff valve. The exible
gas line must be the last item installed on
the gas piping.
Nails or
Wood
Screws
Nailing
Flanges
Figure 9 - Attaching Fireplace to Wall Studs
Wall Studs
4. If you have not assembled rebox, follow
instructions beginning on page 5.
5. Carefully set replace in front of rough
opening with back of replace inside wall
opening.
6. Attach exible gas line to replace gas
regulator. See Connecting Fireplace to
Gas Supply, page 17.
7. Bend four nailing anges on outer casing
with pliers (see Figure 9).
8. Attach replace to wall studs using nails
or wood screws through holes in nailing
ange.
9. Check all gas connections for leaks. See
Checking Gas Connections, page 19.
10. If using optional trim kit, install the trim
after nal nishing and/or painting of wall.
See instructions included with trim acces-
sory for attaching trim.
IMPORTANT: When nishing your rebox,
combustible materials such as wall board,
gypsum board, sheet rock, drywall, plywood,
etc. may be butted up next to the sides and
top edge of the rebox. Combustible materials
should never overlap the rebox front facing.
WARNING: Do not allow any