Avalon Stoves Freestanding Stove Stove User Manual


 
Installation (for qualified installers only) 11
Travis Industries 93508115 4050113
Vent Requirements
! Always maintain the required 1 clearance (air space) to combustible materials to prevent a fire hazard.
Do not fill air spaces with insulation.
! The gas appliance and vent system must be vented directly to the outside of the building, and never
be attached to a chimney serving a separate solid fuel or gas-burning appliance. Each direct vent gas
appliance must use its own separate vent system.
This appliance is equipped only for
altitudes 0-2000 feet. However,
our in-house testing has shown
that the unit operated at altitudes to
8000 ft.
! Failure to adjust the air shutter
properly may lead to improper
combustion which can create a
safety hazard. Consult your dealer
or installer if you suspect an
improperly adjusted air shutter.
When the vent passes through a
wall, a wall thimble is required.
When the vent passes through a
ceiling, a support box or firestop is
required. When the vent passes
through the roof, a roof flashing
and storm collar are required.
Follow the instructions provided
with the vent for installing these
items.
Use a firestop spacer whenever
passing through a ceiling
Vertical Termination
NOTE: always
use the "high-wind" version (if
applicable)
Use a roof flashing and storm collar
whenever passing through the roof
Use a support box
on exposed vent
Vertical Vent
Requirements
Use a firestop whenever
passing through a wall
Horizontal Termination
Maintain a minimum 1"
clearance from vent to any
combustible.
Minimum
Framing for
wall thimble
Horizontal Vent
Requirements
Minimum framing
for fire stop
Maintain a minimum 1"
clearance from vent to
any combustible
8-5/8"
8-5/8"
Use of of the following 6-5/8" diameter co-axial gas direct vent systems:
Manuafacturer Series
Simpson Dura-Vent Model GS
Selkirk Hearth Products Direct-Temp
American Metal Products Ameri-Vent
NOTE : Always use the high-wind cap for the type of vent you are using (if applicable)
Slide the vent sections together and turn 1/4 turn until the sections lock in place.
Screws are not required to secure the vent. However, three screws may be used to
secure vent sections together if desired.
High temperature sealant is recommended at the appliance starter section connection
(use high-temperature silicone or Mill-Pac®).
If disassembly is required, at time of re-assembly check to see if the vent creates a tight
fit. If it does not, apply high temperature sealant to the joints of the affected sections.
Horizontal sections require a 1/4" rise every 12" of travel
Horizontal sections require non-combustible support every three feet (e.g.: plumbing
tape)