Prepare boiler — place in position
Boiler is heavy and contains some
sheet metal parts which may have
sharp edges. Wear gloves when
handling and take proper precautions
when moving. Failure to do so will
result in severe personal injury, death
or substantial property damage.
After installing vent starter tee, inspecting (replacing if
necessary) the gas/air orifice and installing the high
altitude kit (if required), move the boiler near its position.
Figure 6 shows the boiler with the front and top panels
replaced. These panels may be left off if desired until the
installation has been completed.
Refer to Figure 6 for placement sequence:
➀➀
➀➀
➀
Wearing heavy gloves, carefully rotate the boiler
over onto its base rail legs.
➁➁
➁➁
➁
Clip the shipping strap securing the skid to the
boiler block assembly. Remove the skid and strap.
➂➂
➂➂
➂
Attach the jacket rear panel as shown using (4)
#10 x ¾" screws provided in the accessory bag.
Position boiler