Toshiba RAV-SP240AT2-UL Air Conditioner User Manual


 
Toshiba
–15–
Outdoor Unit
Installation Manual
Wiring
1. Remove the front panel and remove the front pipe
cover.
2. Remove the wire cover from back of the front pipe
cover.
3. Pass the wires through the conduit connection holes
and attach the conduit connecters.
4. Connect the wires to the terminal blocks and fix the
wires to the wiring guide with the 2 included banding
band.
L1 L2
L1 L2 S
Field power supply
terminal block
Field power
supply wires
Ground screw
System
interconncection
terminal block
Ground screw
Banding band
System
interconnection
wires
Remove the 4
screws.
Front pipe cover
Cable cove
r
Wire cover
Conduit connector
Terminal block
Do not make the
wires slack in this
section.
Fix with the 2
banding band.
Wire guide
15-EN
+00EH99865401_00Ta.book Page 15 Wednesday, November 25, 2009 11:19 AM