Rinnai E75CP Boiler User Manual


 
Installation & Servicing Instructions Rinnai E-Series
55
Ionization test gure 23
Installing casing gure 24
12.6 Measuring the ionization current
- Switch off the system using the Central Heating button and the DHW button
- Disconnect the plug and the socket
connection on the probe and connect the
measuring device in series. See gure 23.
Select the µA direct current range on the measuring
device. The measuring device must have a resolution
of at least 1 µA.
- Switch on the sytem using the Central Heating button
and the DHW button.
- Press the MODE-button for 5 seconds.
- The display will show COdE followed by an arbitrary
number;
- Select by means of the
or the button the code C123;
- Press the Store-button to conrm the code (code blinks 1 x);
- Press the MODE-button until SERV is shown;
- Press the STEP-button once until 1 is shown;
alternately 1 and OFF will be shown.
- Press the
button until the maximum value (in kW) is achieved;
The boiler will burn on full load (value on display in kW)
value in BTU/hr = x3415
- Measure the ionization. When the boiler is in full load the ionization current must
be > 4 µA and write down this value in the log book.
- Press the
button until OFF is shown (keep button pressed).
- Switch off the system using the Central Heating button and the DHW button
- Disconnect the measuring device and restore the plug and the socket connection
on the probe.
- Switch on the sytem using the Central Heating button and the DHW button.
12.7 Installing the casing
- Install the cover on the boiler and clos all 4
quick releases of the casing
- Tighten the 4 screws A,B,C and D in the quick releases (gure 24);
- Tighten the screw E behind the door on the front of the casing (gure 24);