Raypak 0133-4001 Boiler User Manual


 
Fig. # 8167
MODELS 962-1826
Locate and assemble as shown below. Secure with
screws supplied in envelope in carton.
Fig. # 8165
MODELS 2100-4001
These models have built-in drafthoods. For proper
operation, the drafthood outlet must be connected to
the venting system.
MODELS 514-824
Locate and assemble as shown below. Secure with
screws supplied in envelope in carton.
MODELS 181-401 and 182-400
VENT TERMINAL/INDOOR STACK
INSTALLATION
1. Remove the louvered jacket top by removing
four (4) #10 flathead screws.
2. If originally installed, remove "Pagoda" top
from the louvered jacket top.
3. Place the inner stack adapter panel over the
flue collector inside the heater. Make sure
the flanged side of the flue opening is up.
4. Turn the stack (drafthood) upside
down and set it down bottom side up.
5. Turn the jacket top panel (removed in step 1)
upside down and place it through the stack.
6. Attach the three (3) mounting brackets to the
stack using the screws provided and the holes
that are pre-drilled in the stack. Make sure the
brackets are positioned with the flange near the
top side of the stack (see illustration 8246.5).
Caution must be taken not to over tighten and
strip the screw threads.
7. Turn the assembled stack and jacket top, right side
up. The jacket top will be trapped between the
brackets and the top of the stack. Place the stack
over the inner adapter panel flanged hole and
lower the louvered jacket top panel back into its
original position. Reinstall the four (4) green #10
flathead screws removed in step 1 above.
13
Fig. # 8246.5