If unit is to be “built in”, fireplace framing can be built before or after the appliance is set in place.

Construct fireplace framing
following . The framing headers may rest directly on top of the firebox.
The fireplace may be installed directly on a combustible floor or a raised platform of an appro-
priate height. Do not place fireplace on carpeting, vinyl, tile or other soft floor coverings. It may,
however, be placed on flat wood, plywood, particle board or other hard surfaces. Be sure fire-
place rests on a solid continuous floor or platform with appropriate framing for support and so
that no cold air can enter from under the firebox.
Anchor fireplace to the side framing members using nailing flanges.




1. Secure nailing flanges to side of firebox. 
. Slide the firebox into prepared framing or position firebox in its final position and frame
later.
3. Level the firebox by checking the top edge of the firebox. Shim if necessary.
4. Anchor firebox to the side framing members using 8d nails or other suitable fasteners. 
FP2559
nailing flange
Nail Sides
Through
Nailing
Flanges
FP559
Figure 8 -
Nailing Flanges
FP2558
nailing flanges
5/8" Spacing
1/" Spacing
FP558
Figure 7 -
Nailing Flanges