Heatiator IDV4833IT Indoor Fireplace User Manual


 
Heatilator • ICON DV-IDV Series • 4042-575 • Rev. S • 5/1128
WALL
1-1/2 in.
(38 mm)
3 in.
(76 mm)
No combustible
framing to be
located within
shaded area.
2 x 4 or
2 x 6
header
Sheetrock
Air space clearance to
bottom and sides of
horizontal pipe must be
at least 1 in. (25 mm)
Framing should be
constructed of 2 X 4
lumber or heavier.
The center of the
framing hole is
1 in. (25mm) above
the center of the
horizontal vent pipe.
A*
Vent framing hole.
DO NOT PACK WITH
INSULATION OR
OTHER MATERIAL.
* To center of pipe.
10 in.
12 in.
Appliance A
IDV4833 64-1/8 in./1629 mm
IDV6247 68-5/8 in./1743 mm
A. Pipe Clearances to Combustibles
WARNING! Risk of Fire! Maintain air space clearance to
vent. DO NOT pack insulation or other combustibles:
• Between ceiling restops
Between wall shield restops
Around vent system
Failure to keep insulation or other material away from
vent pipe may cause over heating and re.
8
8
Vent Clearances and Framing
B. Wall Penetration Framing
Combustible Wall Penetration
Whenever a combustible wall is penetrated, you must
frame a hole for the wall shield restop(s). The wall shield
restop maintains minimum clearances and prevents cold
air in ltration.
The opening must be framed on all four sides using the
same size framing materials as those used in the wall
construction.
SLP pipe - A wall shield restop must be placed on each
side of an interior wall. A minimum 1 1/2 in. (38 mm)
overlap of attached heat shields must be maintained.
DVP pipe - A wall shield restop is required on one side
only on interior walls. If your local inspector requires a
wall shield restop on both sides, then both wall shield
restops must have a heat shield attached to them.
See Section 10.I. & 10.J. for information for regarding
the installation of a horizontal termination cap.
Figure 8.2 Wall Penetration
Figure 8.1 Vent Pipe and Horizontal Venting Clearances To Com-
bustible Materials
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by non-combus-
tible materials such as concrete, a hole with diameter one
inch greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall
shield restop is only required on one side and no heat
shield is necessary.
3 in. (76 mm)
top clearance
1 in. (25 mm)clearance
bottom & sides
1 in. (25 mm)
clearance
around vertical
sections
3 in. (76 mm)
top clearance
1 in. (25 mm)
clearance
bottom & sides
Heat
Shield
Wall
Shield
Firestop
Heat
Shield
WALL
Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm). The
heat shield is designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to
184 mm) thick. If wall thickness is less than 4 in. (102 mm) the existing heat
shields must be field trimmed. If wall thickness is greater than 7-1/4 in. (184
mm) a DVP-HSM-B will be required.