TABLE 2: Minimum Installation Clearances To
Combustible Materials (Inches)
A. INSPECT SHIPMENT carefully for any signs of
damage.
1. ALL EQUIPMENT is carefully manufactured,
inspected and packed. Our responsibility ceases
upon delivery of crated boiler to the carrier in good
condition.
2. ANY CLAIMS for damage or shortage in shipment
must be filed immediately against the carrier by the
consignee. No claims for variances from, or
shortage in orders, will be allowed by the
manufacturer unless presented within sixty (60)
days after receipt of goods.
B. LOCATE BOILER in front of final position before
removing crate. See Figures 1A thru 1E.
1. LOCATE so that smoke pipe connection to
chimney will be short and direct. BOILER IS
SUITABLE FOR INSTALLATION ON
COMBUSTIBLE FLOOR. Boiler cannot be
installed on carpeting.
2. FOR BASEMENT INSTALLATION, provide a
solid base, such as concrete, if floor is not level, or
if water may be encountered on floor around boiler.
3. PROVIDE SERVICE CLEARANCE of at least 24”
on right side of boiler for removal of rear tankless
heater. Provide at least 24” clearance from front
jacket panel for servicing and removal of front
tankless heater (increase to 30" for #A54 heater).
Provide at least 24" clearance from right side of
boiler or top of boiler for cleaning flueways. Boiler
flueways may be cleaned either from the top or
from the side.
4. For minimum clearances to combustible materials.
See Table 2.
C. PROVIDE AIR SUPPLY AND VENTILATION to
accommodate proper combustion. If natural ventilation
is inadequate, provide a screened opening or duct from
the boiler room to the outside. The opening or duct
must be sized so the boiler input will not exceed 4,000
BTUH/Sq. In. of free area. If other air consuming
appliances are near the boiler, the air inlet should be
larger. Consult respective manufacturers.
Boiler
A
Above
B
Front
C
Chimney
Connector
D
Rear
E
Sides
V7 6 24 18 6 6
NOTE 1: Listed clearances comply with American
National Standard ANSI/NFPA 31, Installation of Oil
Burning Equipment.
NOTE 2: V7 Series boilers can be installed in rooms
with clearances from combustible material as listed
above. Listed clearances cannot be reduced for
alcove or closet installations.
NOTE 3: For reduced clearances to combustible
material, protection must be provided as described in