START-UP CHECKLIST
(Remove and Store in Job File)
I. PRELIMINARY INFORMATION
MODEL NO.:
DATE:
SERIAL NO.:
TECHNICIAN:
II. PRE-START-UP (insert checkmark in box as each item is completed)
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED AS SHOWN IN THE INSTALLATION
INSTRUCTIONS
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
CHECK THAT INDOOR AIR FILTERS ARE CLEAN AND IN PLACE
VERIFY THAT UNIT INSTALLATION IS LEVEL WITHIN TOLERANCES LISTED IN THE INSTALLATION
INSTRUCTIONS
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW
TIGHTNESS
CHECK PULLEY ALIGNMENT AND BELT TENSION: REFER TO INSTALLATION INSTRUCTIONS
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE L1-L2
L2-L3 L3-L1
COMPRESSOR AMPS L1 L2 L3
INDOOR FAN AMPS L1 L2 L3
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
DB
RETURN-AIR TEMPERATURE
DB WB
COOLING SUPPLY AIR
PRESSURES
REFRIGERANT SUCTION
PSIG
REFRIGERANT DISCHARGE
PSIG
VERIFY REFRIGERANT CHARGE USING COOLING CHARGING CHARTS ON PAGE 31
VERIFY THAT 3-PHASE SCROLL COMPRESSOR IS ROTATING IN CORRECT DIRECTION (558D072 ONLY)
----------------------------------------------------------------------------------------