Bosch Appliances D9412GV3 Home Security System User Manual


 
D9412GV3/D7412GV3 | Operation and Installation Guide | 4.0 Installation
.
Bosch Security Systems, Inc. | 10/10 | F01U143070-03 17
4.6 Completing the Installation
If not already complete, make the earth ground
connection to Terminal 10 and lock the reset pin in
the closed position.
4.6.1 Charging the Battery
Connect the battery, then the transformer to allow the
control panel to charge the battery while you complete
the installation. Refer to Section 5.0 Power Supply on
page 22 for instructions.
On-board Buzzer Sounds at Power Up and Reset:
The system performs a series of self-diagnostic tests
of hardware, software, and programming at power up
and at reset. The buzzer on the control panel sounds
during the tests. The self-diagnostics tests complete
in approximately 1 to 3 sec.
If the control panel fails any test, the buzzer continues
sounding and a System Trouble message appears at
the keypads.
Touch Terminal 10 First: If the on-board buzzer
sounds briefly when the control panel is touched, any
static charge you carry discharges to the control
panel.
Avoid electrostatic discharge. Always
touch Terminal 10, the earth ground
connection, before beginning work on the
control panel.
If the control panel receives an electrostatic
discharge, it might generate Watchdog Reset and
Param Fail events.
4.6.2 Installing and Wiring Detection Devices
Install and wire detection devices and keypads at their
locations throughout the premises. Do not connect
the control panel yet.
Section 8.0 On-Board Points on page 31 contains
instructions for wiring the on-board points to detection
devices. Section 11.0 Arming Devices on page 55
contains instructions for wiring the keypads.
Instructions for wiring the off-board point POPIT
sensor loops are found in the instructions packaged
with the POPIT modules.
4.6.3 Installing Modules and Relays
1. Power down the unit by unplugging the
transformer and disconnecting the battery.
Always power down the unit when
installing modules or relays, or when
making wiring connections to the control
panel.
2. Install and wire any modules required for the
installation as described in the module’s
installation instructions.
Instructions for the D8125 POPEX Module,
D8128D OctoPOPIT Module, D8129 OctoRelay
Module, D811 Arm Status Relay Module, and
D928 Dual Phone Line Switcher appear in this
guide.
Refer to Section 9.0 Off-Board Points on page
36 for D8125 and D8128D instructions. Refer to
Section 10.0 Off-Board Relays on page 50 for
D8129 and D811 instructions. Refer to Section
7.11 D928 Dual Phone Line Switcher on page 30
for D928 instructions.
3. If using the power outputs at Terminals 7 or 8,
refer to Section 6.4 Programmable Power Output
Terminals 6, 7, and 8 on page 27 for
instructions.
4.6.4 Connecting the On-board Points and
Keypads
4. Connect the on-board points and keypad wiring to
the system. Refer to Section 8.0 On-Board Points
on page 31 and Section 11.0 Arming Devices on
page 55 for instructions.
4.6.5 Powering Up
Reconnect the battery, then plug in the transformer.
The buzzer sounds for two sec when the control panel
is powered up. Leave the reset pin in the locked
position.
Yellow Charging Status LED Remains Lit: If the
yellow charging status LED remains lit after five
minutes of powering up the control panel, either the
battery is deeply discharged or too many powered
devices were connected to the control panel.
Combined continuous current draw for Terminals 3, 8,
24, and 32, and the accessory connector cannot
exceed 1.4 A. Refer to Section 6.0 Power Outputs on
page 26 for help.
4.7 Programming the Control Panel
If the control panel is not already programmed, review
the D9412GV3/D7412GV3 Program Entry Guide
(P/N: F01U170807). Ensure that all accessory
modules for desired features are available for
installation.
Use RPS to load a custom program into the control
panel as needed.