Wayne-Dalton DS-100 Door User Manual


 
4
STEP 1 UNPACKING DOORS
Before removing the door from any packaging, inspect the packaging for
visible signs of damage. If damage is noted, file a freight claim with the freight
company immediately. Remove the door from the packaging.
Do not cut tape that holds door
in a roll. You will be told in STEP
#7 when to cut the tape.
No guarantee will be given by Wayne-Dalton if the door is not installed as
instructed. Please review all instructions thoroughly before starting installation. For proper operation, follow these
instructions step by step.
Right and Left Hand is determined by facing the door opening, on the coil
side.
STEP 2 CHECKING THE DOOR OPENING
Verify that dimensions W and H (see below) match those recorded on the door packing slip. Consult the factory if
the actual opening width is greater than that shown on the packing slip by more than 1-1/2 inches. Check to make
certain that the door opening is square and plum and that the floor is level. Check to be certain there is sufficient
clearance from the opening to the ceiling and the sidewalls (see Required Clearances below).
REQUIRED CLEARANCES - MINIMUM INDICATED
OPENING HEIGHT HEADROOM (A) SIDE ROOM (B)
UP TO 6’8” HIGH 13” 4”
FROM 6’8-1/4” TO 8’ HIGH 14” 4”
OVER 8’ HIGH 16” 4”
IMPORTANT!
NOTE: