Installation Checklist
Complete this checklist once the unit
is installed to verify that all recom-
mended procedures have been
accomplished before starting the sys-
tem. Do not operate the system until
all items covered by this checklist are
complete.
[ ] Inspect unit location for proper
required service clearances.
[ ] Inspect unit location for proper free
air clearances.
[ ] Inspect unit location for secure,
level mounting position.
Refrigerant Piping
[ ] Performed initial leak test?
[ ] Connected properly sized and con-
structed liquid and discharge lines
to the connection stubs at both the
indoor and outdoor units?
[ ] Insulated the entire discharge line?
[ ] Insulated portions of liquid line
exposed to extremes in tempera
-
ture?
[ ] Evacuated each refrigerant circuit
to 350 microns?
[ ] Charged each circuit with proper
amount of R-410A?
Electrical Wiring
WARNING:
Hazardous Voltage
w/Capacitors!
Disconnect all electrical power,
including remote disconnects and
discharge all motor start/run ca-
pacitors before servicing. Follow
proper lockout/tagout procedures
to ensure the power cannot be in-
advertently energized. Verify with
an appropriate voltmeter that all
capacitors have discharged. Fail-
ure to diconnect power and dis-
charge capacitors before
servicing could result in death or
serious injury.
Note: For additional information
regarding the safe discharge of
capacitors, see PROD-SVB06A-
EN or PROD-SVB06A-FR.
[ ] Provided unit power wiring (with
disconnect) to proper terminals in
the unit control section?
[ ] Installed system indoor thermo-
stat?
[ ] Installed system low voltage inter-
connecting wiring to proper termi-
nals of outdoor unit, indoor unit
and system thermostat?
System
Pre-Start Procedure