Sterling STT40 Dehumidifier User Manual


 
14.3. Quick Start Guide for STT 70 Dryer
1. Check all wiring connections to ensure that they are in the correct place and have a good tight
connection.
2. Hook up main three-phase power and ground. The following picture shows the correct
location.
Main power High Temp Safety Main Power Connection
Heater Connection Thermocouple
3. Turn the disconnect switch to the “ON” position as shown. The green run light should light up.
4. Turn the dryer operation switch to the desired position. If you have a seven day timer
installed, set it to “On with timer” position, otherwise set it to “On without timer” position. The
blower will start. An explanation is given in the following diagram.
On with timer
On without
timer
OFF