Heat & Glo LifeStyle 704-902 Gas Heater User Manual


 
Heat & Glo • Bravo • 704-902 Rev. E • 7/0818
WALL
HEAT
SHIELD
HEAT
SHIELD
3in.TOP
CLEARANCE
WALL
SHIELD
FIRESTOP
1in.CLEARANCE
BOTTOM & SIDES
Combustible Wall Penetration
Frame a hole in a combustible wall for an interior wall
shield restop, (Figure 6.2) whenever a wall is penetrated.
Use same size framing materials as those used in the wall
construction. The wall shield restop maintains minimum
clearances and prevents cold air in ltration.
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by noncombus-
tible materials such as concrete, a hole with diameter one
inch greater than the pipe is acceptable.
Whenever a non-combustible wall is penetrated, the wall
shield restop is only required on one side and no heat
shield is necessary.
If your local inspector requires the wall shield restop on
both sides, then both wall shield restops must have a heat
shield attached to them.
Fire Risk.
Explosion Risk.
Maintain vent clearance to combustibles as
speci ed.
WARNING
Do not pack air space with insulation or
other materials.
Failure to keep insulation or other materials
away from vent pipe may cause re.
B. Wall Penetration Framing
Figure 6.1 Pipe Clearances
Figure 6.3 Exterior Wall Hole
* Shows center of vent framing hole for top venting. The
center of the hole is one (1) inch (25.4mm) above the
center of the horizontal vent pipe.
Figure 6.2 Horizontal Venting Clearances to Combustible Materials
B
A
10 in.
12 in.
Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).
The heat shield is designed to be used on a wall 4 in. to 7-1/4 in. (102
mm to 184 mm) thick. If wall thickness is less than 4 in. (102 mm) the
existing heat shields must be eld trimmed. If wall thickness is greater than
7-1/4 in. (184 mm) a DVP-HSM-B will be required.
A. Pipe Clearances to Combustibles
6
6
Vent Clearances and Framing
A* B
87-3/4 in. 86-3/4 in.
1 in. CLEARANCE
AROUND VERTICAL
SECTIONS
3 in. TOP
CLEARANCE
1 in. SIDE AND
BOTTOM CLEARANCE