Hearth and Home Technologies Everest Indoor Fireplace User Manual


 
Heat & Glo • Everest • 750-900 Rev. o • 10/08 26
Step 10. Installing Trim, Logs and Ember
Material
Installing the Trim
Combustible materials may be brought up to the speci ed
clearances on the side and top front edges of the replace,
but MUST NEVER overlap onto the front face. The joints
between the nished wall and the replace top and sides
can only be sealed with a 300° F. (149° C) minimum
sealant.
Install optional marble and brass trim surround kits as
desired. Marble, brass, brick, tile, or other non-combustible
materials can be used to cover up the gap between the
sheet rock and the replace.
Positioning the Logs
If the gas logs have been factory installed they should not
need to be positioned. If the logs have been packaged
separately, refer to the instructions that accompany the
logs. Save the log instructions with this manual.
If sooting occurs, the logs might need to be repositioned
slightly to avoid excessive ame impingement.
Placing the Rock
A bag of rock is shipped with this replace. Refer to the
placement instructions on the back of the log placement
instructions.
Placing the Ember Material
Ember material is shipped with this gas replace. The bag
labeled Glowing Ember (050-721) is standard glowing
ember material. To place the ember material:
• Pull the six glass latches out of the groove on the glass
frame. Remove the front trim door and the glass door
from the unit.
• Cover the top of the burner with a single layer of ember
material. For best performance do not place embers di-
rectly on the ports. Save the remaining ember materials
for use during replace servicing.
• Replace the glass door and a front trim door on the unit
(see Service Parts List of this manual.)
• Pull out and latch the glass clips into the groove on the
glass frame.
Glass Speci cations: CERAMIC
Figure 27. Placement of the Ember Material
Figure 26. Glass Assembly
EMBER
MATERIAL
LATCHES
GLASS
ASSEMBLY