Drolet SIT 0.820.634 Stove User Manual


 
ULTRA FLAME DIRECT VENT GAS STOVE 12
Direct Vent Kit for Basement Installation
1. Move the stove to its position;
2. Install temporary an 8 in.
section (4) to visualize where
the opening to be done thru the
wall. Center of the opening
should be at about 23 ½ “above
the base of the stove;
Note: Horizontal run should have a
slope of ¼ in per foot.
3. Make a 10-1/2" x 10-1/2"
opening in the wall, 23-1/2"
inches in order to introduce the
radiation shield thru the wall;
4. Cut the radiation shield to
length if necessary and install
as shown. Secure with four #10
1” wood screws;
5. Install the vent terminal (13)
with 2 ½ screws (12). You may
want to remove the vent casing
for easy access and
manipulation, Keep only in
place the wall plate;
Basement Installation
6. Insert the 8 in. pipe into the round
opening of the interior black wall
plate (7). Fix the insulation pad (9)
around the 8 in. pipe with the
aluminum tape;
7. Keeping the insulation joint of the 8
in. pipe down, insert it into the vent
terminal wall plate;
8. Secure the 8 in. pipe to vent terminal
wall plate with the metal screw;
9. Fix finally the vent terminal wall plate
with six 2 ½ in screws (12).
10. Insert the 5 in. flexible pipe (3) into
the 8 in. pipe and fix it to the vent
terminal casing. Use high
temperature silicone and one
locking band to secure it in pace;
NOTE: All joints must be sealed with
RTV silicone, 315°C. (600°F)
temperature resistance.
CUT TO LENGTH
10-1/2" X 10-1/2"
OPENING